Digging

Our house is built on a rock, as you can see at the bottom of the wall.

IMG_20160422_092926.jpg
rocks and stones

Before pouring the concrete foundation, we need a nice level ground floor. So, a while ago, we started digging out the house ourselves, with a pickaxe and a shovel… Needless to say, we gave up pretty quickly and decided to call in the big guns.

We took advantage of the digger who came to do the trench for the water pipe and had him dig out the inside of the house. The week before, we took out as much as we could by hand, but what we did in an hour, he did in about a minute.

First, he dug out in front of the entrance to be able to get inside with his excavator.

DSC07261.JPG
the digging begins

Then he preceded to dig out about 2 feet of dirt and huge stones. He put it all right outside to extend the terrace.

DSC07265.JPG
a bit more efficient than a pickaxe

And here are the after photos! A little scary to see the bottom of the house just kind of sitting on the rock. Every time we go up, we cross our fingers that it hasn’t fallen down.

DSC07273.JPG
the wall is gone!
DSC07280.JPG
the rock
DSC07277.JPG
view from above
DSC07282.JPG
ground floor entrance inside
DSC07279.JPG
ground floor entrance outside

He also leveled out the path leading down to the ground floor. I could almost make it down in my Clio.

DSC07278.JPG
path

Now the main path is more or less passable (depending on how much it’s rained) and the roofers are doing their thing. It’s awesome having building professionals working on the house, because they get so much more done than we ever could on our own. Writing them a huge check is a little less awesome.

Up next, the roof!

In the trenches

Lots of goings on at the house!

We had the terrasier (digger, navvy??) around for a week, digging the trench for the water and then digging out the ground floor (which I’ll show you next time).  A super nice guy who has more or less worked for everyone in the village.

Google maps said that it’s 185 meters from the house down to the water tower where they put our hook-up. He started at the top and dug a trench 1 meter deep all the way down.

DSC07235.JPG
the trench! and the “garage”
DSC07250
hard at work
DSC07249
inside
DSC07253
the hook-up

Then he laid the water pipe, covered it with a bit of sand, and closed it all up.

So it’s great having water, but we miss our nice little path up to the house! Now it looks like this:

DSC07259

But that means that the roofers can make it up in their truck, most of the time, anyways. It rained a lot the other day and the trail was super muddy. Hopefully it will get better over time!

Next time I’ll show you what he did to the inside of the house.