So, here we are 3 years later. Confined for a global pandemic, so a good time to update the blog, I guess?? We can’t go to the hardware store to get any building materials, though we’ve still got plenty we can do. So how about a stroll down memory lane. Well, for me at least.
Work on the floor went through several steps, but since I’m in the future, I can show you everything at once. This was basically all we did in 2017 – it took a while to prepare it all, and I wasn’t much help since I was pregnant most of the year!
The first layer is flagstones (from the roof, mostly).


Next came the gravel. There are drainage pipes under the gravel, guess I forgot to take a picture of that!




And finally, pouring the concrete floor. We thought it best to leave it to the professionals. A plastic barrier was put down to prevent water coming up. And then the expansion joints were put in (that’s what they’re called, right?)

In addition to pouring the concrete floor in the main part of the house and the bathroom, we also had them create a step up to the doorway to the bathroom, since it’s a bit higher than the main house.

Then they placed the wire mesh and began pouring. In the bathroom picture, you can see some of the pipes that we put in place for drainage, waste water and recovering rainwater (I’ll do a post on that another time).


And the finished product! It goes pretty quickly when the pros do it – too bad you have to pay them. Here’s the finished bathroom floor.


And the main house.


Ok, that wasn’t so hard. Sorry it’s taken so long! With a baby (sleep-deprived mama), jobs and setbacks (you’ll see…) it’s been a bit hard to find the motivation to write it all out. Coming up in 2018 – beams, windows, doors and more floors.