The floor

So, here we are 3 years later. Confined for a global pandemic, so a good time to update the blog, I guess?? We can’t go to the hardware store to get any building materials, though we’ve still got plenty we can do. So how about a stroll down memory lane. Well, for me at least.

Work on the floor went through several steps, but since I’m in the future, I can show you everything at once. This was basically all we did in 2017 – it took a while to prepare it all, and I wasn’t much help since I was pregnant most of the year!

The first layer is flagstones (from the roof, mostly).

IMG_20160923_140911
step one – stones
IMG_20160928_100505
leveling

Next came the gravel. There are drainage pipes under the gravel, guess I forgot to take a picture of that!

DSC07439
gravel
DSC07443
gravel
DSC07445
gravel
20170910_152507
bathroom with future shower drain

And finally, pouring the concrete floor. We thought it best to leave it to the professionals. A plastic barrier was put down to prevent water coming up. And then the expansion joints were put in (that’s what they’re called, right?)

DSC07462
placing the expansion joints

In addition to pouring the concrete floor in the main part of the house and the bathroom, we also had them create a step up to the doorway to the bathroom, since it’s a bit higher than the main house.

20171030_153259
form for the step

Then they placed the wire mesh and began pouring. In the bathroom picture, you can see some of the pipes that we put in place for drainage, waste water and recovering rainwater (I’ll do a post on that another time).

DSC07469
starting to pour the concrete over the wire mesh
DSC07458
bathroom side

And the finished product! It goes pretty quickly when the pros do it – too bad you have to pay them. Here’s the finished bathroom floor.

DSC07465
bathroom from above
DSC07467
bathroom from door

And the main house.

20171103_135800
the step
20171103_135519
panorama

Ok, that wasn’t so hard. Sorry it’s taken so long! With a baby (sleep-deprived mama), jobs and setbacks (you’ll see…) it’s been a bit hard to find the motivation to write it all out. Coming up in 2018 – beams, windows, doors and more floors.

A garden and a doorway

Hi there, it’s been a while. I felt like there hadn’t been any major progress, so I didn’t really know what to post about. Plus, life kind of got in the way. But now that I’m looking back to find pictures, there’s a whole lot I can show you. Two things in particular: the garden and the bathroom.

So when I left off, we had finished the roof. You can see it here along with recent progress on the future vegetable garden.

almost like a real house

For reference, here’s what the vegetation looked like before. And an action shot of the brush-cutting which T did in February. 99% him by the way. I threw some branches on the fire but that’s about it.

before … and burning

On to the bathroom, which will be in the lean-to on the left side of the house. After our roofers finished, half of the old roof was inside the lean-to, so we had to dig it out (I actually did help with that!). And once we did, we got to the rock that the house is built on. We had a mini rock quarry operation going on, where T excavated slabs of rock to try and get a level ground.

left-July, right-October

Now that it was a bit cleaned up, we could call on our father-son roofing-masonry  team to come and open up a doorway between the main house and the bathroom.

lintel in place, stones coming down on the son side
the father side
the opening complete, beginning to concrete

And finally, the finished product. Since the bathroom is higher than the main house, the stairs will go down from the front door, stop at a landing in front of the door to the bathroom, then turn back down towards the ground floor.

view from the front door … and back up

More views

from the main house … looking down into the bathroom from the front

Next up is getting everything ready to pour the concrete floor in both the main house and the bathroom. Which means more digging, putting in drains (inside and outside), leveling, and then a whole bunch of layers of stuff to keep out the humidity and solidify the floor.

A bientôt!

The roof – part 3: tiles!

I was waiting to be completely done with the roof before posting, but since it’s ALMOST done and we’ve already moved on to other things, here’s the final installment.

Last you read, the roof panels were up and the gutters put in. We could have left it at that, but to better protect the roof and also to make it perty, we added tiles. T saw a sign on the side of the road a few months ago: “Tuiles à vendre”, so we were able to get some cheap used tiles. New ones would have stood out too much, and did I mention they were cheap?

They were just 10 minutes up the road, sold by the brother of our wood guy. There were 1300 of them to somehow get up to the house. The first attempt was in my Clio with our neighbor’s trailer.

IMG_20160521_152936.jpg
la remorque

I have no idea how to drive with a trailer, and the extra weight meant that we couldn’t take a whole lot at a time. We wound up putting down the back seat and transporting the tiles directly in the car. After consulting the owner’s manual on weight limits for my car and doing a bit of math, we figured we could take about 150 each trip.

Since my car can’t make it up the path to the house, we stopped at the bottom and wheelbarrowed them up to the water tower.

IMG_20160604_152318.jpg
halfway there

Our very helpful neighbor got the tractor of another very helpful neighbor and helped us get them all the way up to the house.

IMG_20160604_153524.jpg
trip 1 of 3
DSC07337
tiles ready

The roofers left the scaffolding in place so that we could get on to the roof. To hold the tiles in place on the panels, we used hooks that I didn’t take a picture of. We started by drilling a hole 9 cm from the bottom of each of the rows for the first hook.

DSC07338.JPG
measuring

The tile slides right in to the bottom hook, you add another hook to the top and then slide on the next tile.

DSC07340.JPG
5 tiles down

Easy enough, until you get to the top of a line or around the skylight and a whole tile won’t fit, which means it needs to be cut. Also easy enough with a circular saw, except that we don’t have electricity. So we went out a bought a generator.

IMG_20160610_172858.jpg
marking out the cut
IMG_20160610_143029.jpg
cutting the tiles
IMG_20160612_115244.jpg
somewhat precise cuts

The hardest part was actually getting the tiles up to the roof. I could only carry three at a time up the ladder, but we still knocked it out in about 3 days. We wound up using around 800 tiles.

We still need to finish the edges, but the roof is 99% done.

DSC07349.JPG
tiles!
DSC07353.JPG
you can’t tell but there are tiles, promise

Right now we’re finishing cleaning out the debris, and picking away at the rock to make it as uniform as possible. We hope to be pouring the foundation in about two weeks, which means putting in drainage, deciding on where to put pipes, and way more stuff I’m sure!